14th Aug 2010

10h00 – The pan for the day is to correctly connected the underfloor heating on the upper mezzanine.   So its of to Gien to buy paint for the Kitchen walls, a shade of orange that has to be mixed. … Continue reading

Posted in Uncategorized | Leave a comment

13th Aug 2010

09h30 – Today is the day for connecting up the upper mezzanine underfloor heating.    I had bought all the parts last year. 14h00 – No a good job, soldering, push fits and screw fits in copped and PER (plastic). … Continue reading

Posted in Uncategorized | Leave a comment

12th Aug 2010

10h00 – So, its definitely the day to drain the heating system.  This was achieved.   The towel radiator in the kitchen was removed and laid outside on the table.   This was a good opportunity to see how it … Continue reading

Posted in Uncategorized | Leave a comment

11th Aug 2010

10h00 – The plan for the day is to drain the heating system and change the central heating main pump.    I do not have to drain the complete system to do this but P wants to  finish decorating behind … Continue reading

Posted in Uncategorized | Leave a comment

10th Aug 2010

08h30 – Barry and Pat were off to Rouen today on their journey home to Wellingborough.  After a good breakfast they left just before mid-day and were going via Paris. L’Echiquier web-site.

Posted in Uncategorized | Leave a comment