09h30 – Today is the day for connecting up the upper mezzanine underfloor heating.    I had bought all the parts last year.

14h00 – No a good job, soldering, push fits and screw fits in copped and PER (plastic).  A really messy job and a few drip leaks where PTFE tape was used.   I was NOT pleased with he result and decided it had to be done again using the existing valves for the lower mezzanine.   The result would be only one set of valves for all the mezzanine heating.  So  a list of parts I needed was made.  P said she needed paint so should we go to Gien to get some.   We decided to fix the leaks as best I could and shut off the heating but get the hot water back on then go to Gien tomorrow.